Paracatu de Baixo


The works for the resettlement of Paracatu de Baixo, district of Mariana (MG), continue with the construction of houses and more than 90% of the infrastructure completed. Until the district is built and the housing is completed, the provision of temporary housing to families who have this right is guaranteed.
The process involved the active participation of around 78 families, from choosing the land to monitoring the construction of the new district. Community involvement brought to the proposal characteristics in line with collective habits. The construction of the treated water pipeline and works on the storm drain and sewage network have already been carried out. The school works are in progress and the paving of the main access road has been completed. Nine permits were issued for the use of collective goods, such as kindergarten and elementary schools, sports courts, advanced health posts, service centers, fields, chapels, Casa São Vicente and community hall. For the houses, 50 permits were issued and the basic projects are being filed.

THE DISTRICT

Located 35 kilometers from Mariana (MG), Paracatu de Baixo is a sub-district of the city of Monsenhor Horta (MG) and is crossed by the Gualaxo do Norte River. In the region there are properties with plantations and a predominance of subsistence activities. One of the most traditional festivities celebrated by the community is the Folia de Reis festival, held between Christmas and Three Kings Day. The Folia de Reis do Menino Jesus, another highly visible religious festival in the region, is celebrated in September.

In September 2016, the community of Paracatu de Baixo chose the land for the new district. The area has 84.8 hectaresand is also located in Monsenhor Horta. With the participation of the families, the characteristics of the infrastructure, such as schools, churches, squares, health centers, will be preserved. Community practices are references to reestablish economic, productive and cultural activities in the new district. Follow the progress of the work in the resettlement of Paracatu de Baixo below.

In February 2022, the construction of the treated water pipeline and works of the storm drain network were carried out, and more than 90% of the infrastructure was completed.
In February 2022, the construction of the treated water pipeline and works of the storm drain network were carried out, and more than 90% of the infrastructure was completed.
In August 2021, the paving of the main access road to the resettlement began.
In August 2021, the paving of the main access road to the resettlement began.
In June 2021, the assembly of the school structure was completed.
In June 2021, the assembly of the school structure was completed.
In March 2021, the works to contain the slopes and highways at the interchange of the new access road to the resettlement were completed.
In March 2021, the works to contain the slopes and highways at the interchange of the new access road to the resettlement were completed.
In July 2020, excavation works began on the foundations of the Municipal School of Paracatu de Baixo.
In July 2020, excavation works began on the foundations of the Municipal School of Paracatu de Baixo.
In December 2019, work began on the foundations of the houses
In December 2019, work began on the foundations of the houses
In July 2019, the developmental approval was issued, enabling the start of earthworks and infrastructure works.
In July 2019, the developmental approval was issued, enabling the start of earthworks and infrastructure works.
In December 2018, the installation of the construction site began on the land chosen by the community
In December 2018, the installation of the construction site began on the land chosen by the community
In February 2022, the construction of the treated water pipeline and works of the storm drain network were carried out, and more than 90% of the infrastructure was completed.
In August 2021, the paving of the main access road to the resettlement began.
In June 2021, the assembly of the school structure was completed.
In March 2021, the works to contain the slopes and highways at the interchange of the new access road to the resettlement were completed.
In July 2020, excavation works began on the foundations of the Municipal School of Paracatu de Baixo.
In December 2019, work began on the foundations of the houses
In July 2019, the developmental approval was issued, enabling the start of earthworks and infrastructure works.
In December 2018, the installation of the construction site began on the land chosen by the community

Virtual Tour

Tools
  • Toogle Forplan Toogle Forplan
  • Toogle Gallery Toogle Gallery
  • Intro Popup Intro Popup
  • Little Planet Little Planet
  • Fullscreen Fullscreen

Follow here the progress of the works of the new districts of Bento Rodrigues, in Mariana (MG). The images are updated weekly and you can access the monthly history of the Virtual Tour.

Rotate your phone to landscape Rotate your phone to landscape.

Access the tour start view Access the tour start view.

Learn more about each location Learn more about each location.

Navigate with the buttons or open the auxiliary map Navigate with the buttons or open the auxiliary map.

Share:

Leave your comment